22-9-604. Procedure.

(a) (1) In the case of a construction contract entered into between a public agency and a contractor who is required to furnish a performance bond, the contractor shall be entitled to payment of ninety-five percent (95%) of the earned progress payments when due, with the public agency retaining five percent (5%) to assure faithful performance of the contract.

(2) If the construction contract allows for phased work in which completion may occur on a partial occupancy, any retention proceeds withheld and retained under this section shall be partially released within thirty (30) days under the same conditions under this section in direct proportion to the value of the part of the capital improvement completed.

(b) All sums withheld by the public agency shall be paid to the contractor within thirty (30) days after the construction contract has been completed.

(c) In the event the construction contract requires the contractor to purchase and furnish materials or equipment that will be stored on the job site or in a bonded warehouse by the contractor and used in the job as required by the construction contract, no retainage will be withheld on that amount of the submitted progress payment pertaining to the cost of these stored materials or equipment.

Arkansas Forms by Issue

Arkansas Appeals Forms
Arkansas Auto Accident Forms
Arkansas Child Support Agency Forms
Arkansas Court Forms
> Substance Abuse
Arkansas Divorce Forms
Arkansas Family Forms
Arkansas Tax Forms

Arkansas Law

Arkansas State Laws
    > Arkansas Child Support
    > Arkansas Gun Laws
    > Arkansas Statute
Arkansas State
    > Arkansas State Parks
Arkansas Tax
    > Arkansas State Tax
Arkansas Agencies
    > Arkansas Department of Corrections
    > Arkansas Department of Education
    > Arkansas Federal Credit Union
    > Arkansas Secretary of State
    > Arkansas State Police

Arkansas Court Map

Tips