CONNECTICUT STATUTES AND CODES
               		Sec. 16-244j. Electric transmission lines from Bethel to Norwalk. Moratorium. Working group and comprehensive assessment.
               		
               		
               	 	
               	 	               	 	
               	 	
               	 	
               	 		
      Sec. 16-244j. Electric transmission lines from Bethel to Norwalk. Moratorium. Working group and comprehensive assessment. (a) Notwithstanding any other 
provision of the general statutes, no state agency, including, but not limited to, the 
Department of Environmental Protection and the Connecticut Siting Council, shall render a final decision for any applications relating to electric transmission lines from Bethel 
to Norwalk including, but not limited to, applications that are pending or received on 
and after June 3, 2002, until February 1, 2003. During such interim period, the Institute 
for Sustainable Energy shall chair and convene a working group comprised of: (1) Two 
representatives chosen by the chief elected officials of Bethel, Redding, Weston, Wilton 
and Norwalk, one of whom shall have environmental expertise and one of whom shall 
have energy expertise; (2) one representative of the Connecticut Fund for the Environment; (3) two representatives of the applicant company; and (4) one representative of 
the New England Independent System Operator, Inc. and develop a comprehensive 
assessment and report on: (A) The economic considerations and environmental preferences and appropriateness of installing such transmission lines underground or overhead; (B) the feasibility of meeting all or part of the electric power needs of the region 
through distributive generation; and (C) the electric reliability, operational and safety 
concerns of the region's transmission system and the technical and economic feasibility 
of addressing those concerns with currently available electric transmission system 
equipment. The Institute for Sustainable Energy shall publish its report on or before 
January 1, 2003, and shall also include recommendations for any legislative changes 
deemed necessary as a result of such assessment. Any decision or opinion rendered on 
any application for an electric transmission line from Bethel to Norwalk by either the 
Department of Environmental Protection or the Connecticut Siting Council after the 
publication of such comprehensive assessment and report, shall be evaluated to determine such application's consistency with such assessment. Nothing in this section shall 
be construed to prevent routine maintenance and repair of such electric transmission 
lines.
      (b) Any applicant that elects to proceed with its application for an electric transmission line from Bethel to Norwalk before any state agency, including, but not limited to, 
the Department of Environmental Protection and the Connecticut Siting Council, during 
the interim period described in subsection (a) of this section, shall accrue no legal rights 
or financial entitlements by proceeding with its application.
      (P.A. 02-95, S. 2.)