Sec. 16a-38g. Decision schedule. (a) The commissioner shall issue a decision
schedule for each priority energy project within sixty days after his designation. Such
decision schedule shall state the order in which agency decisions are to be made and
where feasible shall provide for concurrent review of applications and joint agency
hearings. Notwithstanding any general statute or special act to the contrary, such decision schedule shall provide, whenever deemed in the best interests of the state by said
commissioner, for the completion of all agency decisions within one year or less from
the date of its issuance.
(b) Notwithstanding the provisions of any general statutes or special act to the contrary, if the time limit set forth in the decision schedule for an agency decision has
elapsed and such decision has not been made, it shall be deemed to have been made in
favor of the project unless the commissioner waives or grants an extension of such
time limit.