Sec. 22a-6q. Alternative time frame for action on permit.
Sec. 22a-6q. Alternative time frame for action on permit. When the commissioner determines, based on the size, novelty, complexity or technical difficulty of a
project, that work cannot be completed within the schedule for timely action applicable
to a permit application pursuant to subdivision (3) of section 22a-6p, the commissioner
shall notify the applicant of such determination within thirty days of receiving the permit
application and shall, within forty-five days of providing such notice, establish an alternative permit schedule for timely action.
(P.A. 95-218, S. 21, 24; P.A. 96-118, S. 1.)
History: P.A. 95-218, S. 21 effective July 6, 1995; P.A. 96-118 made a technical correction to an internal reference.