Sec. 4b-103. Construction manager at-risk project delivery contracts.
Sec. 4b-103. Construction manager at-risk project delivery contracts. (a) In
order to carry out any provision of this title for the construction, renovation or alteration
of buildings or facilities, the Commissioner of Public Works may enter into a construction manager at-risk project delivery contract.
(b) The Commissioner of Public Works shall not enter into a construction manager
at-risk project delivery contract that does not provide for a maximum guaranteed price
for the cost of construction that shall be determined not later than the time of the receipt
and approval by the commissioner of the trade contractor bids. Each construction manager at-risk shall invite bids and give notice of opportunities to bid on project elements,
by advertising, at least once, in one or more newspapers having general circulation in
the state. Each bid shall be kept sealed until opened publicly at the time and place as
set forth in the notice soliciting such bid. The construction manager at-risk shall, after
consultation with and approval by the commissioner, award any related contracts for
project elements to the responsible qualified contractor submitting the lowest bid in
compliance with the bid requirements, provided (1) the construction manager at-risk
shall not be eligible to submit a bid for any such project element, and (2) construction
shall not begin prior to the determination of the maximum guaranteed price, except for
the project elements of site preparation and demolition that have been previously put
out to bid and awarded.
(P.A. 06-134, S. 21.)