GEORGIA STATUTES AND CODES
               		§ 13-10-80 - Definitions; contract requirements; application; effect of  greater benefits contracted for; evidence of indebtedness paid
               		
               		
               	 	
               	 	               	 	
               	 	
               	 	
               	 		
O.C.G.A.    13-10-80   (2010)
    13-10-80.    Definitions; contract requirements; application; effect of  greater benefits contracted for; evidence of indebtedness paid 
      (a)  As used in this Code section, the term:
      (1)  "Contractor" means a person having a direct contract with the owner.
      (2)  "Lower tier subcontractor" means a person other than a contractor having a direct contract with a subcontractor.
      (3)  "Owner"  means the state, any county, municipal corporation, authority, board of  education, or other public board, public body, department, agency,  instrumentality, or political subdivision of the state.
      (4)  "Owner's  authorized contract representative" means the architect or engineer in  charge of the project for the owner or such other contract  representative or officer as designated in the contract documents as the  party representing the owner's interest regarding administration and  oversight of the project.
      (5)  "Subcontractor" means a person other than an owner having a direct contract with the contractor.
(b)  In  any public works construction contract entered into on or after July 1,  2001, with an owner, as defined in paragraph (3) of subsection (a) of  this Code section, such contract shall provide for the following:
      (1)  After  work has commenced at the construction site, progress payments to be  made on some periodic basis, and at least monthly, based on the value of  work completed as may be provided in the contract documents plus the  value of materials and equipment suitably stored, insured, and protected  at the construction site and at the owner's discretion such materials  and equipment suitably stored, insured, and protected off site at a  location approved by the owner's authorized contract representative when  allowed by the contract documents, less retainage; and
            (2)(A)  Retainage  to a maximum of 10 percent of each progress payment; provided, however,  when 50 percent of the contract value including change orders and other  additions to the contract value provided for by the contract documents  is due and the manner of completion of the contract work and its  progress are reasonably satisfactory to the owner's authorized contract  representative, the owner shall withhold no more retainage. At the  discretion of the owner and with the approval of the contractor, the  retainage of each subcontractor may be released separately as the  subcontractor completes his or her work.
            (B)  If,  after discontinuing the retention, the owner's authorized contract  representative determines that the work is unsatisfactory or has fallen  behind schedule, retention may be resumed at the previous level. If  retention is resumed by an owner, the contractor and subcontractors  shall be entitled to resume withholding retainage accordingly.
            (C)  At  substantial completion of the work or such other standard of completion  as may be provided in the contract documents and as the owner's  authorized contract representative determines the work to be reasonably  satisfactory, the owner shall, within 30 days after invoice and other  appropriate documentation as may be required by the contract documents  are provided, pay the retainage to the contractor. If at that time there  are any remaining incomplete minor items, an amount equal to 200  percent of the value of each item as determined by the owner's  authorized contract representative shall be withheld until such item or  items are completed. The reduced retainage shall be shared by the  contractor and subcontractors as their interests may appear.
            (D)  The  contractor shall, within ten days from the contractor's receipt of  retainage from the owner, pass through payments to subcontractors and  shall reduce each subcontractor's retainage in the same manner as the  contractors retainage is reduced by the owner; provided, however, that  the value of each subcontractor's work complete and in place equals 50  percent of his or her subcontract value, including approved change  orders and other additions to the subcontract value, provided, further,  that the work of the subcontractor is proceeding satisfactorily and the  subcontractor has provided or provides such satisfactory reasonable  assurances of continued performance and financial responsibility to  complete his or her work including any warranty work as the contractor  in his or her reasonable discretion may require, including, but not  limited to, a payment and performance bond.
            (E)  The  subcontractor shall, within ten days from the subcontractor's receipt  of retainage from the contractor, pass through payments to lower tier  subcontractors and shall reduce each lower tier subcontractor's  retainage in the same manner as the subcontractors retainage is reduced  by the contractor; provided, however, that the value of each lower tier  subcontractor's work complete and in place equals 50 percent of his or  her subcontract value, including approved change orders and other  additions to the subcontract value; provided, further, that the work of  the lower tier subcontractor is proceeding satisfactorily and the lower  tier subcontractor has provided or provides such satisfactory reasonable  assurances of continued performance and financial responsibility to  complete his or her work including any warranty work as the  subcontractor in his or her reasonable discretion may require,  including, but not limited to, a payment and performance bond.
(c)  This Code section shall not apply to:
      (1)  Any  contracts let by the Department of Transportation of this state for the  construction, improvement, or maintenance of roads or highways in this  state or purposes incidental thereto; or
      (2)  Any contracts whose value or duration at the time of the award does not exceed $150,000.00 or 45 days in duration.
(d)  Contract  and subcontract provisions inconsistent with the benefits extended to  contractors, subcontractors, and lower tier subcontractors by this Code  section shall be unenforceable; provided, however, that nothing in this  Code section shall render unenforceable any contract or subcontract  provisions allowing greater benefits to be extended to such contractors,  subcontractors, or lower tier subcontractors, the provisions and  benefits of this Code section being minimal only.
(e)  Nothing  shall preclude a payor under this Code section, prior to making a  payment, from requiring the payee to submit satisfactory evidence that  all payrolls, material bills, and other indebtedness connected with the  work have been paid.