      (1)  "Capacity resource" means an electric plant, a long-term power purchase, or a demand-side capacity option.
      (2)  "Commission" means the Georgia Public Service Commission.
      (3)  "Construction"  means clearing of land, excavation, or other substantial activity  leading to the operation of an electric plant other than planning, land  surveying, land acquisition, subsurface exploration, design work,  licensing or other regulatory activity, contracting for construction, or  environmental protection measures and activities associated therewith.
      (4)  "Demand-side  capacity option" means a program proposed by a utility or the  commission for the reduction of future electricity requirements the  utility's Georgia retail customers would otherwise impose, including,  but not limited to, conservation, load management, cogeneration, and  renewable energy technologies.
      (5)  "Electric  plant" means any facility, or the portion of a facility, that produces  electricity or that, at the time application for certification is made  pursuant to this chapter, is intended to produce electricity for a  utility's Georgia retail customers.  "Electric plant" includes the  realty and ancillary facilities for the construction of the plant.
      (6)  "Long-term  power purchase" means a purchase of electric capacity and energy for a  period exceeding one year, the principal purpose of which is to supply  the requirements of the Georgia retail customers of a utility.
      (7)  "Plan"  means an integrated resource plan which contains the utility's electric  demand and energy forecast for at least a 20 year period, contains the  utility's program for meeting the requirements shown in its forecast in  an economical and reliable manner, contains the utility's analysis of  all capacity resource options, including both demand-side and  supply-side options, and sets forth the utility's assumptions and  conclusions with respect to the effect of each capacity resource option  on the future cost and reliability of electric service. The plan shall  also:
            (A)  Contain the size and type  of facilities which are expected to be owned or operated in whole or in  part by such utility and the construction of which is expected to  commence during the ensuing ten years or such longer period as the  commission deems necessary and shall identify all existing facilities  intended to be removed from service during such period or upon  completion of such construction;
            (B)  Contain  practical alternatives to the fuel type and method of generation of the  proposed electric generating facilities and set forth in detail the  reasons for selecting the fuel type and method of generation;
            (C)  Contain  a statement of the estimated impact of proposed and alternative  generating plants on the environment and the means by which potential  adverse impacts will be avoided or minimized;
            (D)  Indicate  in detail the projected demand for electric energy for a 20 year period  and the basis for determining the projected demand;
            (E)  Describe the utility's relationship to other utilities in regional associations, power pools, and networks;
            (F)  Identify  and describe all major research projects and programs which will  continue or commence in the succeeding three years and set forth the  reasons for selecting specific areas of research;
            (G)  Identify  and describe existing and planned programs and policies to discourage  inefficient and excessive power use; and
            (H)  Provide any other information as may be required by the commission.
      (8)  "Supply-side  capacity option" means an electric plant, a long-term power purchase,  or any other source of additional energy.
      (9)  "Utility" means any electric supplier whose rates are fixed by the commission.
               	 	
               	 	
               	 	               	 	
               	 	               	 	               	  
               	 
               	 
               	 
               	 