Title 35-A: PUBLIC UTILITIES HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
Part 3: ELECTRIC POWER HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
Chapter 43: NUCLEAR POWER GENERATING FACILITIES HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
Subchapter 4: SPENT FUEL AND HIGH-LEVEL WASTE REQUIREMENTS HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
If the conditions of section 4374 have not been met, the commission may continue to receive and process applications for certification, but may not certify a nuclear power plant. Any other governmental entity which grants necessary permits, licenses, approvals or authorizations for construction of a nuclear power plant may process and grant those permits, licenses, approvals or authorizations, subject to the commission's granting of certification under this chapter. [1987, c. 141, Pt. A, §6 (NEW).]
SECTION HISTORY
1987, c. 141, §A6 (NEW).