Find Laws Find Lawyers Free Legal Forms USA State Laws

MASSACHUSETTS STATUTES AND CODES

Section 39O Contracts for construction and materials; suspension, delay or interruption due to order of awarding authority; adjustment in contract price; written claim

Section 39O. Every contract subject to the provisions of section thirty-nine M of this chapter or subject to section forty-four A of chapter one hundred forty-nine shall contain the following provisions (a) and (b) in their entirety and, in the event a suspension, delay, interruption or failure to act of the awarding authority increases the cost of performance to any subcontractor, that subcontractor shall have the same rights against the general contractor for payment for an increase in the cost of his performance as provisions (a) and (b) give the general contractor against the awarding authority, but nothing in provisions (a) and (b) shall in any way change, modify or alter any other rights which the general contractor or the subcontractor may have against each other.

(a) The awarding authority may order the general contractor in writing to suspend, delay, or interrupt all or any part of the work for such period of time as it may determine to be appropriate for the convenience of the awarding authority; provided however, that if there is a suspension, delay or interruption for fifteen days or more or due to a failure of the awarding authority to act within the time specified in this contract, the awarding authority shall make an adjustment in the contract price for any increase in the cost of performance of this contract but shall not include any profit to the general contractor on such increase; and provided further, that the awarding authority shall not make any adjustment in the contract price under this provision for any suspension, delay, interruption or failure to act to the extent that such is due to any cause for which this contract provides for an equitable adjustment of the contract price under any other contract provisions.

(b) The general contractor must submit the amount of a claim under provision (a) to the awarding authority in writing as soon as practicable after the end of the suspension, delay, interruption or failure to act and, in any event, not later than the date of final payment under this contract and, except for costs due to a suspension order, the awarding authority shall not approve any costs in the claim incurred more than twenty days before the general contractor notified the awarding authority in writing of the act or failure to act involved in the claim.

Massachusetts Forms by Issue

Massachusetts Abortion Forms
Massachusetts Business Forms
Massachusetts Court Forms
> DUI
> Claims
> Personal Protection
Massachusetts Divorce Forms
Massachusetts Family Forms
Massachusetts Guardianship Forms
Massachusetts Gun Forms
Massachusetts Marriage Forms
Massachusetts Name Change Forms
Massachusetts Tax Forms

Massachusetts Law

Massachusetts State Laws
    > Massachusetts Statutes
    > Massachusetts Gun Laws
    > Child Support Massachusetts
Massachusetts State
    > Capital of Massachusetts
    > Massachusetts Counties
Massachusetts Court
    > Massachusetts Attorney General
    > Massachusetts v. EPA
Massachusetts Tax
    > Massachusetts Sales Tax
    > Massachusetts State Tax
Massachusetts Labor Laws
    > Jobs In Massachusetts
    > Massachusetts Unemployment
Massachusetts Agencies
    > Better Business Bureau Massachusetts
    > Food Stamps Massachusetts
    > Massachusetts Department of Education
    > Massachusetts Department of Public Health
    > Massachusetts Department of Revenue
    > Massachusetts DMV
    > Massachusetts Secretary of State Corporations
    > Massachusetts State Police
    > Massachussets Secretary of State

Massachusetts Court Map

Tips