460.1175 Net metering; application fee; limitation; costs; interconnection requirements.

Sec. 175.

(1) An electric utility or alternative electric supplier may charge a fee not to exceed $100.00 to process an application for net metering. A customer with a system capable of generating more than 20 kilowatts shall pay all interconnection costs. A customer with a system capable of generating more than 150 kilowatts shall pay standby costs. The commission shall recognize the reasonable cost for each electric utility and alternative electric supplier to operate a net metering program. For an electric utility with 1,000,000 or more retail customers in this state, the commission shall include in that utility's nonfuel base rates all costs of meeting all program requirements except that all energy costs of the program shall be recovered through the utility's power supply cost recovery mechanism under sections 6j and 6k of 1939 PA 3, MCL 460.6j and 460.6k. For an electric utility with less than 1,000,000 base distribution customers in this state, the commission shall allow that utility to recover all energy costs of the program through the power supply cost recovery mechanism under sections 6j and 6k of 1939 PA 3, MCL 460.6j and 460.6k, and shall develop a cost recovery mechanism for that utility to contemporaneously recover all other costs of meeting the program requirements.

(2) The interconnection requirements of the net metering program shall provide that an electric utility or alternative electric supplier shall, subject to any time requirements imposed by the commission and upon reasonable written notice to the net metering customer, perform testing and inspection of an interconnected eligible electric generator as is necessary to determine that the system complies with all applicable electric safety, power quality, and interconnection requirements. The costs of testing and inspection are considered a cost of operating a net metering program and shall be recovered under subsection (1).

(3) The interconnection requirements shall require all eligible electric generators, alternative electric suppliers, and electric utilities to comply with all applicable federal, state, and local laws, rules, or regulations, and any national standards as determined by the commission.


History: 2008, Act 295, Imd. Eff. Oct. 6, 2008
Compiler's Notes: Enacting section 1 of Act 295 of 2008 provides:"Enacting section 1. As provided in section 5 of 1846 RS 1, MCL 8.5, this act is severable."

Michigan Forms by Issue

Michigan Abortion Forms
Michigan Adoption Forms
Michigan Appeals Forms
Michigan Business Forms
Michigan Child Support Agency Forms
Michigan Children/Juvenile Forms
Michigan Court Forms
> Criminal
> DUI
> Probate
> Traffic
> Case Evaluation
> Civil (County)
> Civil (District)
> Claims
> Dispute
> Forfeiture
> Garnishment
> Personal Protection
> Probation
> Small Claims
> Substance Abuse
Michigan Emancipation Forms
Michigan Family Forms
Michigan Foreclosure Forms
Michigan Guardianship Forms
Michigan Gun Forms
Michigan Landlord/Tenant Forms
Michigan Marriage Forms
Michigan Name Change Forms
Michigan Other Forms
Michigan Tax Forms

Michigan Law

Michigan State Laws
    > Michigan Child Support
    > Michigan Gun Laws
    > Michigan Statutes
Michigan Court
    > Michigan Court of Appeals
Michigan Tax
    > Michigan State Tax
Michigan Labor Laws
    > Unemployment Michigan
Michigan State
    > Michigan Counties
    > Michigan Zip Codes
Michigan Agencies
    > Department of Human Services Michigan
    > Michigan Department of Corrections
    > Michigan Department of Education
    > Michigan State Police
    > Secretary of State Michigan

Michigan Court Map

Tips