Find Laws Find Lawyers Free Legal Forms USA State Laws

MICHIGAN STATUTES AND CODES

Section 460.10v - Joint plan to expand available transmission capability.

MICHIGAN PUBLIC SERVICE COMMISSION (EXCERPT)
Act 3 of 1939

460.10v Joint plan to expand available transmission capability.

Sec. 10v.

(1) Electric utilities serving more than 100,000 retail customers in this state shall file, by January 1, 2001, a joint plan with the commission detailing measures to permanently expand, within 2 years of the effective date of this section, the available transmission capability by at least 2,000 megawatts over the available transmission capability in place as of January 1, 2000.

(2) The joint plan shall detail all actions including additional facilities required, the proposed schedule for accomplishing the actions, the cost of the actions, and the proposed ratemaking treatment for the costs. The joint plan shall also identify all actions and facilities that are required of other transmission owners, including out-of-state entities, to accommodate the actions described in the joint plan.

(3) The commission may order modifications to the joint plan to make it consistent with this act. If the electric utilities are unable to agree upon a joint plan to meet the requirements of this act, the commission shall conduct a hearing to establish a joint plan. The commission shall authorize recovery from benefitting customers of all reasonable and prudent costs incurred by transmission owners for authorized actions taken and facilities installed to meet the requirements of this section that are not recovered through FERC transmission rates.

(4) If an electric utility or an affiliate that is the owner of the transmission assets is denied cost recovery of the reasonable and prudent costs expended to implement the joint plan, then the electric utility or affiliate shall have no further obligation to implement the joint plan. If an electric utility or its affiliate is subsequently granted cost recovery, then the obligation to implement the original joint plan is required. If cost recovery of the reasonable and prudent costs of implementing the joint plan is denied, an electric utility or its affiliate shall develop a new joint plan as provided under this section.


History: Add. 2000, Act 141, Imd. Eff. June 5, 2000
Popular Name: Customer Choice and Electricity Reliability Act

Michigan Forms by Issue

Michigan Abortion Forms
Michigan Adoption Forms
Michigan Appeals Forms
Michigan Business Forms
Michigan Child Support Agency Forms
Michigan Children/Juvenile Forms
Michigan Court Forms
> Criminal
> DUI
> Probate
> Traffic
> Case Evaluation
> Civil (County)
> Civil (District)
> Claims
> Dispute
> Forfeiture
> Garnishment
> Personal Protection
> Probation
> Small Claims
> Substance Abuse
Michigan Emancipation Forms
Michigan Family Forms
Michigan Foreclosure Forms
Michigan Guardianship Forms
Michigan Gun Forms
Michigan Landlord/Tenant Forms
Michigan Marriage Forms
Michigan Name Change Forms
Michigan Other Forms
Michigan Tax Forms

Michigan Law

Michigan State Laws
    > Michigan Child Support
    > Michigan Gun Laws
    > Michigan Statutes
Michigan Court
    > Michigan Court of Appeals
Michigan Tax
    > Michigan State Tax
Michigan Labor Laws
    > Unemployment Michigan
Michigan State
    > Michigan Counties
    > Michigan Zip Codes
Michigan Agencies
    > Department of Human Services Michigan
    > Michigan Department of Corrections
    > Michigan Department of Education
    > Michigan State Police
    > Secretary of State Michigan

Michigan Court Map

Tips