338.555 - Amounts withheld as retainage; payment of interest.

338.555  Amounts withheld as retainage; payment of interest.

      1.  If a public body and a contractor enter into a contract for a public work, the contractor may withhold as retainage not more than 10 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract. Thereafter the contractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the contractor, satisfactory progress is being made in the work under the subcontract, and the payment must be equal to that paid by the public body to the contractor for the work performed by the subcontractor.

      2.  If the contractor receives a payment of interest earned on the retainage or an amount withheld from a progress payment, the contractor shall, within 10 days after he or she receives the money, pay to each subcontractor or supplier that portion of the interest received from the public body which is attributable to the retainage or amount withheld from a progress payment by the contractor to the subcontractor or supplier.

      (Added to NRS by 1973, 1160; A 1981, 553; 1983, 1592; 1999, 1994)

     

Nevada Forms by Issue

Nevada Business Forms
Nevada Court Forms
> DUI
> Small Claims
Nevada Divorce Forms
Nevada Family Forms
Nevada Guardianship Forms
Nevada Gun Forms
Nevada Insurance Forms
Nevada Name Change Forms
Nevada Tax Forms

Nevada Law

Nevada State Laws
    > Nevada Child Support
    > Nevada Gun Laws
    > Nevada Statutes
Nevada Tax
    > Nevada State Tax
Nevada Labor laws
    > Nevada Unemployment Claims
    > Unemployment Nevada
Nevada Court
    > Nevada Appeal
Nevada Agencies
    > Nevada DMV
    > Nevada Secretary of State Business Search
    > Secretary of State Nevada

Nevada Court Map

Tips