338.590 - Time for making payments; amounts paid.

338.590  Time for making payments; amounts paid.  Except as otherwise provided in NRS 338.595, 338.600 and 338.605:

      1.  Each subcontractor shall disburse money paid to him or her pursuant to this chapter, including any interest which the subcontractor receives, to his or her subcontractors and suppliers within 10 days after the subcontractor receives the money, in direct proportion to the subcontractors’ and suppliers’ basis in the progress bill or retainage bill and any accrued interest thereon.

      2.  A subcontractor shall make payments to his or her subcontractor or supplier in an amount equal to that subcontractor’s or supplier’s basis in the payments paid by the contractor to him or her for the supplies, materials and equipment identified in the contract between the contractor and the public body, or in the subcontract between the subcontractor or supplier and the contractor, within 10 days after the subcontractor has received a progress payment or retainage payment from the contractor for those supplies, materials and equipment.

      (Added to NRS by 1999, 1987)

     

Nevada Forms by Issue

Nevada Business Forms
Nevada Court Forms
> DUI
> Small Claims
Nevada Divorce Forms
Nevada Family Forms
Nevada Guardianship Forms
Nevada Gun Forms
Nevada Insurance Forms
Nevada Name Change Forms
Nevada Tax Forms

Nevada Law

Nevada State Laws
    > Nevada Child Support
    > Nevada Gun Laws
    > Nevada Statutes
Nevada Tax
    > Nevada State Tax
Nevada Labor laws
    > Nevada Unemployment Claims
    > Unemployment Nevada
Nevada Court
    > Nevada Appeal
Nevada Agencies
    > Nevada DMV
    > Nevada Secretary of State Business Search
    > Secretary of State Nevada

Nevada Court Map

Tips