Section 57-28-8 - Final payment.

57-28-8. Final payment.

Ten days after certification of completion, any amounts remaining due the contractor or subcontractor under the terms of the contract shall be paid upon the presentation of the following:   

A.     a properly executed release and duly certified voucher for payment;   

B.     a release, if required, of all claims and claims of lien against the owner arising under and by virtue of the contract other than such claims of the contractor, if any, as may be specifically excepted by the contractor or subcontractor from the operation of the release in stated amounts to be set forth in the release; and   

C.     proof of completion.   

New Mexico Law

New Mexico State Laws
    > New Mexico Child Support
    > New Mexico Gun Laws
    > New Mexico Statutes
New Mexico Tax
    > New Mexico State Tax
New Mexico Labor Laws
    > New Mexico Unemployment
New Mexico Agencies
    > New Mexico DMV
    > New Mexico Taxation and Revenue

New Mexico Court Map

Tips