66-34-204. Payment of retainage by owner.
When an owner:
(1) Has received a use and/or occupancy permit for an improvement from a governmental agency lawfully issuing such permit;
(2) Has received a certificate of substantial completion from an architect charged with supervision of the construction of an improvement; or
(3) Begins to use or could have begun to use an improvement;
the owner shall, after any such event and pursuant to the terms of the written contract, pay to the contractor all retainage the owner may have withheld pursuant to the written contract, except any sum which the owner may reasonably withhold in accordance with provisions of the written contract between the owner and the contractor; provided, however, that the retainage must be paid within ninety (90) days after the date of the occurrence of an event included in subdivision (1), (2) or (3).
[Acts 1991, ch. 45, § 1; 2007, ch. 201, § 5.]