PROPERTY CODE
TITLE 5. EXEMPT PROPERTY AND LIENS
SUBTITLE B. LIENS
CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
SUBCHAPTER A. GENERAL PROVISIONS
Sec. 53.001. DEFINITIONS. In this chapter:
(1) "Contract price" means the cost to the owner for any part of
construction or repair performed under an original contract.
(2) "Improvement" includes:
(A) abutting sidewalks and streets and utilities in or on those
sidewalks and streets;
(B) clearing, grubbing, draining, or fencing of land;
(C) wells, cisterns, tanks, reservoirs, or artificial lakes or
pools made for supplying or storing water;
(D) pumps, siphons, and windmills or other machinery or
apparatuses used for raising water for stock, domestic use, or
irrigation; and
(E) planting orchard trees, grubbing out orchards and replacing
trees, and pruning of orchard trees.
(3) "Labor" means labor used in the direct prosecution of the
work.
(4) "Material" means all or part of:
(A) the material, machinery, fixtures, or tools incorporated
into the work, consumed in the direct prosecution of the work, or
ordered and delivered for incorporation or consumption;
(B) rent at a reasonable rate and actual running repairs at a
reasonable cost for construction equipment used or reasonably
required and delivered for use in the direct prosecution of the
work at the site of the construction or repair; or
(C) power, water, fuel, and lubricants consumed or ordered and
delivered for consumption in the direct prosecution of the work.
(5) "Mechanic's lien" means the lien provided by this chapter.
(6) "Original contract" means an agreement to which an owner is
a party either directly or by implication of law.
(7) "Original contractor" means a person contracting with an
owner either directly or through the owner's agent.
(8) "Residence" means a single-family house, duplex, triplex, or
quadruplex or a unit in a multiunit structure used for
residential purposes that is:
(A) owned by one or more adult persons; and
(B) used or intended to be used as a dwelling by one of the
owners.
(9) "Residential construction contract" means a contract between
an owner and a contractor in which the contractor agrees to
construct or repair the owner's residence, including improvements
appurtenant to the residence.
(10) "Residential construction project" means a project for the
construction or repair of a new or existing residence, including
improvements appurtenant to the residence, as provided by a
residential construction contract.
(11) "Retainage" means an amount representing part of a contract
payment that is not required to be paid to the claimant within
the month following the month in which labor is performed,
material is furnished, or specially fabricated material is
delivered. The term does not include retainage under Subchapter
E.
(12) "Specially fabricated material" means material fabricated
for use as a component of the construction or repair so as to be
reasonably unsuitable for use elsewhere.
(13) "Subcontractor" means a person who has furnished labor or
materials to fulfill an obligation to an original contractor or
to a subcontractor to perform all or part of the work required by
an original contract.
(14) "Work" means any part of construction or repair performed
under an original contract.
(15) "Completion" of an original contract means the actual
completion of the work, including any extras or change orders
reasonably required or contemplated under the original contract,
other than warranty work or replacement or repair of the work
performed under the contract.
Acts 1983, 68th Leg., p. 3533, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 2, eff.
Sept. 1, 1997; Acts 1999, 76th Leg., ch. 889, Sec. 1, eff. Sept.
1, 1999.
Sec. 53.002. MORE THAN ONE ORIGINAL CONTRACTOR. On any work
there may be more than one original contractor for purposes of
this chapter.
Acts 1983, 68th Leg., p. 3535, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.003. NOTICES. (a) This section applies to notices
required by Subchapters B through G and K.
(b) Any notice or other written communication may be delivered
in person to the party entitled to the notice or to that party's
agent, regardless of the manner prescribed by law.
(c) If notice is sent by registered or certified mail, deposit
or mailing of the notice in the United States mail in the form
required constitutes compliance with the notice requirement. This
subsection does not apply if the law requires receipt of the
notice by the person to whom it is directed.
(d) If a written notice is received by the person entitled to
receive it, the method by which the notice was delivered is
immaterial.
Acts 1983, 68th Leg., p. 3535, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 3, eff.
Sept. 1, 1997.
SUBCHAPTER B. PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY
Sec. 53.021. PERSONS ENTITLED TO LIEN. (a) A person has a lien
if:
(1) the person labors, specially fabricates material, or
furnishes labor or materials for construction or repair in this
state of:
(A) a house, building, or improvement;
(B) a levee or embankment to be erected for the reclamation of
overflow land along a river or creek; or
(C) a railroad; and
(2) the person labors, specially fabricates the material, or
furnishes the labor or materials under or by virtue of a contract
with the owner or the owner's agent, trustee, receiver,
contractor, or subcontractor.
(b) A person who specially fabricates material has a lien even
if the material is not delivered.
(c) An architect, engineer, or surveyor who prepares a plan or
plat under or by virtue of a written contract with the owner or
the owner's agent, trustee, or receiver in connection with the
actual or proposed design, construction, or repair of
improvements on real property or the location of the boundaries
of real property has a lien on the property.
(d) A person who provides labor, plant material, or other
supplies for the installation of landscaping for a house,
building, or improvement, including the construction of a
retention pond, retaining wall, berm, irrigation system,
fountain, or other similar installation, under or by virtue of a
written contract with the owner or the owner's agent, trustee, or
receiver has a lien on the property.
(e) A person who performs labor as part of, or who furnishes
labor or materials for, the demolition of a structure on real
property under or by virtue of a written contract with the owner
of the property or the owner's agent, trustee, receiver,
contractor, or subcontractor has a lien on the property.
Acts 1983, 68th Leg., p. 3535, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 395, Sec. 1, eff.
Sept. 1, 1989; Acts 1989, 71st Leg., ch. 1138, Sec. 1, eff. Sept.
1, 1989; Acts 1991, 72nd Leg., ch. 16, Sec. 16.01, eff. Aug. 26,
1991; Acts 1995, 74th Leg., ch. 851, Sec. 1, 6, eff. Sept. 1,
1995; Acts 1999, 76th Leg., ch. 896, Sec. 1, eff. Sept. 1, 1999;
Acts 2003, 78th Leg., ch. 410, Sec. 1, eff. Sept. 1, 2003.
Sec. 53.022. PROPERTY TO WHICH LIEN EXTENDS. (a) The lien
extends to the house, building, fixtures, or improvements, the
land reclaimed from overflow, or the railroad and all of its
properties, and to each lot of land necessarily connected or
reclaimed.
(b) The lien does not extend to abutting sidewalks, streets, and
utilities that are public property.
(c) A lien against land in a city, town, or village extends to
each lot on which the house, building, or improvement is situated
or on which the labor was performed.
(d) A lien against land not in a city, town, or village extends
to not more than 50 acres on which the house, building, or
improvement is situated or on which the labor was performed.
Acts 1983, 68th Leg., p. 3536, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.023. PAYMENT SECURED BY LIEN. The lien secures payment
for:
(1) the labor done or material furnished for the construction or
repair;
(2) the specially fabricated material, even if the material has
not been delivered or incorporated into the construction or
repair, less its fair salvage value; or
(3) the preparation of a plan or plat by an architect, engineer,
or surveyor in accordance with Section 53.021(c).
Acts 1983, 68th Leg., p. 3536, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1995, 74th Leg., ch. 851, Sec. 2, eff.
Sept. 1, 1995.
Sec. 53.024. LIMITATION ON SUBCONTRACTOR'S LIEN. The amount of
a lien claimed by a subcontractor may not exceed:
(1) an amount equal to the proportion of the total subcontract
price that the sum of the labor performed, materials furnished,
materials specially fabricated, reasonable overhead costs
incurred, and proportionate profit margin bears to the total
subcontract price; minus
(2) the sum of previous payments received by the claimant on the
subcontract.
Acts 1983, 68th Leg., p. 3536, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.025. LIMITATION ON ORDINARY RETAINAGE LIEN. A lien for
retainage is valid only for the amount specified to be retained
in the contract, including any amendments to the contract,
between the claimant and the original contractor or between the
claimant and a subcontractor.
Acts 1983, 68th Leg., p. 3537, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 2, eff.
Sept. 1, 1989.
Sec. 53.026. SHAM CONTRACT. (a) A person who labors, specially
fabricates materials, or furnishes labor or materials under a
direct contractual relationship with another person is considered
to be in direct contractual relationship with the owner and has a
lien as an original contractor, if:
(1) the owner contracted with the other person for the
construction or repair of a house, building, or improvements and
the owner can effectively control that person through ownership
of voting stock, interlocking directorships, or otherwise;
(2) the owner contracted with the other person for the
construction or repair of a house, building, or improvements and
that other person can effectively control the owner through
ownership of voting stock, interlocking directorships, or
otherwise; or
(3) the owner contracted with the other person for the
construction or repair of a house, building, or improvements and
the contract was made without good faith intention of the parties
that the other person was to perform the contract.
(b) In this section, "owner" does not include a person who has
or claims a security interest only.
Acts 1983, 68th Leg., p. 3537, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 3, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 4, eff. Sept.
1, 1997.
SUBCHAPTER C. PROCEDURE FOR PERFECTING LIEN
Sec. 53.051. NECESSARY PROCEDURES. To perfect the lien, a
person must comply with this subchapter.
Acts 1983, 68th Leg., p. 3538, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.052. FILING OF AFFIDAVIT. (a) Except as provided by
Subsection (b), the person claiming the lien must file an
affidavit with the county clerk of the county in which the
property is located or into which the railroad extends not later
than the 15th day of the fourth calendar month after the day on
which the indebtedness accrues.
(b) A person claiming a lien arising from a residential
construction project must file an affidavit with the county clerk
of the county in which the property is located not later than the
15th day of the third calendar month after the day on which the
indebtedness accrues.
(c) The county clerk shall record the affidavit in records kept
for that purpose and shall index and cross-index the affidavit in
the names of the claimant, the original contractor, and the
owner. Failure of the county clerk to properly record or index a
filed affidavit does not invalidate the lien.
Acts 1983, 68th Leg., p. 3538, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 4, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 5, eff. Sept.
1, 1997.
Sec. 53.053. ACCRUAL OF INDEBTEDNESS. (a) For purposes of
Section 53.052, indebtedness accrues on a contract under which a
plan or plat is prepared, labor was performed, materials
furnished, or specially fabricated materials are to be furnished
in accordance with this section.
(b) Indebtedness to an original contractor accrues:
(1) on the last day of the month in which a written declaration
by the original contractor or the owner is received by the other
party to the original contract stating that the original contract
has been terminated; or
(2) on the last day of the month in which the original contract
has been completed, finally settled, or abandoned.
(c) Indebtedness to a subcontractor, or to any person not
covered by Subsection (b) or (d), who has furnished labor or
material to an original contractor or to another subcontractor
accrues on the last day of the last month in which the labor was
performed or the material furnished.
(d) Indebtedness for specially fabricated material accrues:
(1) on the last day of the last month in which materials were
delivered;
(2) on the last day of the last month in which delivery of the
last of the material would normally have been required at the job
site; or
(3) on the last day of the month of any material breach or
termination of the original contract by the owner or contractor
or of the subcontract under which the specially fabricated
material was furnished.
(e) A claim for retainage accrues on the last day of the month
in which all work called for by the contract between the owner
and the original contractor has been completed, finally settled,
or abandoned.
Acts 1983, 68th Leg., p. 3539, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 5, eff.
Sept. 1, 1989; Acts 1995, 74th Leg., ch. 851, Sec. 3, eff. Sept.
1, 1995.
Sec. 53.054. CONTENTS OF AFFIDAVIT. (a) The affidavit must be
signed by the person claiming the lien or by another person on
the claimant's behalf and must contain substantially:
(1) a sworn statement of the amount of the claim;
(2) the name and last known address of the owner or reputed
owner;
(3) a general statement of the kind of work done and materials
furnished by the claimant and, for a claimant other than an
original contractor, a statement of each month in which the work
was done and materials furnished for which payment is requested;
(4) the name and last known address of the person by whom the
claimant was employed or to whom the claimant furnished the
materials or labor;
(5) the name and last known address of the original contractor;
(6) a description, legally sufficient for identification, of the
property sought to be charged with the lien;
(7) the claimant's name, mailing address, and, if different,
physical address; and
(8) for a claimant other than an original contractor, a
statement identifying the date each notice of the claim was sent
to the owner and the method by which the notice was sent.
(b) The claimant may attach to the affidavit a copy of any
applicable written agreement or contract and a copy of each
notice sent to the owner.
(c) The affidavit is not required to set forth individual items
of work done or material furnished or specially fabricated. The
affidavit may use any abbreviations or symbols customary in the
trade.
Acts 1983, 68th Leg., p. 3540, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 6, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 6, eff. Sept.
1, 1997.
Sec. 53.055. NOTICE OF FILED AFFIDAVIT. (a) A person who files
an affidavit must send a copy of the affidavit by registered or
certified mail to the owner or reputed owner at the owner's last
known business or residence address not later than the fifth day
after the date the affidavit is filed with the county clerk.
(b) If the person is not an original contractor, the person must
also send a copy of the affidavit to the original contractor at
the original contractor's last known business or residence
address within the same period.
Acts 1983, 68th Leg., p. 3540, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 7, eff.
Sept. 1, 1989; Acts 1993, 73rd Leg., ch. 48, Sec. 7, eff. Sept.
1, 1993; Acts 1997, 75th Leg., ch. 526, Sec. 7, eff. Sept. 1,
1997; Acts 1999, 76th Leg., ch. 889, Sec. 2, eff. Sept. 1, 1999.
Sec. 53.056. DERIVATIVE CLAIMANT: NOTICE TO OWNER OR ORIGINAL
CONTRACTOR. (a) Except as provided by Subchapter K, a claimant
other than an original contractor must give the notice prescribed
by this section for the lien to be valid.
(b) If the lien claim arises from a debt incurred by a
subcontractor, the claimant must give to the original contractor
written notice of the unpaid balance. The claimant must give the
notice not later than the 15th day of the second month following
each month in which all or part of the claimant's labor was
performed or material delivered. The claimant must give the same
notice to the owner or reputed owner and the original contractor
not later than the 15th day of the third month following each
month in which all or part of the claimant's labor was performed
or material or specially fabricated material was delivered.
(c) If the lien claim arises from a debt incurred by the
original contractor, the claimant must give notice to the owner
or reputed owner, with a copy to the original contractor, in
accordance with Subsection (b).
(d) To authorize the owner to withhold funds under Subchapter D,
the notice to the owner must state that if the claim remains
unpaid, the owner may be personally liable and the owner's
property may be subjected to a lien unless:
(1) the owner withholds payments from the contractor for payment
of the claim; or
(2) the claim is otherwise paid or settled.
(e) The notice must be sent by registered or certified mail and
must be addressed to the owner or reputed owner or the original
contractor, as applicable, at his last known business or
residence address.
(f) A copy of the statement or billing in the usual and
customary form is sufficient as notice under this section.
Acts 1983, 68th Leg., p. 3540, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 8, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 8, eff. Sept.
1, 1997.
Sec. 53.057. DERIVATIVE CLAIMANT: NOTICE FOR CONTRACTUAL
RETAINAGE CLAIM. (a) A claimant may give notice under this
section instead of or in addition to notice under Section 53.056
or 53.252 if the claimant is to labor, furnish labor or
materials, or specially fabricate materials under an agreement
with an original contractor or a subcontractor providing for
retainage.
(b) The claimant must give the owner or reputed owner notice of
the retainage agreement not later than the 15th day of the second
month following the delivery of materials or the performance of
labor by the claimant that first occurs after the claimant has
agreed to the contractual retainage. If the agreement is with a
subcontractor, the claimant must also give notice within that
time to the original contractor.
(c) The notice must contain:
(1) the sum to be retained;
(2) the due date or dates, if known; and
(3) a general indication of the nature of the agreement.
(d) The notice must be sent by registered or certified mail to
the last known business or residence address of the owner or
reputed owner or the original contractor, as applicable.
(e) If a claimant gives notice under this section and Section
53.055 or, if the claim relates to a residential construction
project, under this section and Section 53.252, the claimant is
not required to give any other notice as to the retainage.
Acts 1983, 68th Leg., p. 3541, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 9, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 9, eff. Sept.
1, 1997; Acts 1999, 76th Leg., ch. 889, Sec. 3, eff. Sept. 1,
1999.
Sec. 53.058. DERIVATIVE CLAIMANT: NOTICE FOR SPECIALLY
FABRICATED ITEMS. (a) Except as provided by Subchapter K, a
claimant who specially fabricates material must give notice under
this section for the lien to be valid.
(b) The claimant must give the owner or reputed owner notice not
later than the 15th day of the second month after the month in
which the claimant receives and accepts the order for the
material. If the indebtedness is incurred by a person other than
the original contractor, the claimant must also give notice
within that time to the original contractor.
(c) The notice must contain:
(1) a statement that the order has been received and accepted;
and
(2) the price of the order.
(d) The notice must be sent by registered or certified mail to
the last known business or residence address of the owner or the
reputed owner or the original contractor, as applicable.
(e) In addition to notice under this section, the claimant must
give notice under Section 53.056 if delivery has been made or if
the normal delivery time for the job has passed.
(f) The lien of a claimant who accepts an order but fails to
give notice under this section is valid as to delivered items if
the claimant has given notice under Section 53.056.
(g) If a retainage agreement consists in whole or part of an
obligation to furnish specially fabricated materials and the
claimant has given notice under Section 53.057, the claimant is
not required to give notice under this section.
Acts 1983, 68th Leg., p. 3542, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 10, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 10, eff. Sept.
1, 1997.
SUBCHAPTER D. FUNDS WITHHELD BY OWNER FOLLOWING NOTICE
Sec. 53.081. AUTHORITY TO WITHHOLD FUNDS FOR BENEFIT OF
CLAIMANTS. (a) If an owner receives notice under Section
53.056, 53.057, 53.058, 53.252, or 53.253, the owner may withhold
from payments to the original contractor an amount necessary to
pay the claim for which he receives notice.
(b) If notice is sent in a form that substantially complies with
Section 53.056 or 53.252, the owner may withhold the funds
immediately on receipt of the notice.
(c) If notice is sent under Section 53.057, the owner may
withhold funds immediately on receipt of a copy of the claimant's
affidavit prepared in accordance with Sections 53.052 through
53.055.
(d) If notice is sent under Section 53.058, the owner may
withhold funds immediately on receipt of the notices sent under
Subsection (e) of that section. If notice is sent as provided by
Section 53.253(b), the owner may withhold funds immediately on
receipt of the notice sent as required by Section 53.252.
Acts 1983, 68th Leg., p. 3543, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 12, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 11, eff. Sept.
1, 1997.
Sec. 53.082. TIME FOR WHICH FUNDS ARE WITHHELD. Unless payment
is made under Section 53.083 or the claim is otherwise settled,
discharged, indemnified against under Subchapter H or I, or
determined to be invalid by a final judgment of a court, the
owner shall retain the funds withheld until:
(1) the time for filing the affidavit of mechanic's lien has
passed; or
(2) if a lien affidavit has been filed, until the lien claim has
been satisfied or released.
Acts 1983, 68th Leg., p. 3544, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 13, eff.
Sept. 1, 1989.
Sec. 53.083. PAYMENT TO CLAIMANT ON DEMAND. (a) The claimant
may make written demand for payment of the claim to an owner
authorized to withhold funds under this subchapter. The demand
must give notice to the owner that all or part of the claim has
accrued under Section 53.053 or is past due according to the
agreement between the parties.
(b) The claimant must send a copy of the demand to the original
contractor. The original contractor may give the owner written
notice that the contractor intends to dispute the claim. The
original contractor must give the notice not later than the 30th
day after the day he receives the copy of the demand. If the
original contractor does not give the owner timely notice, he is
considered to have assented to the demand and the owner shall pay
the claim.
(c) The claimant's demand may accompany the original notice of
nonpayment or of a past-due claim and may be stamped or written
in legible form on the face of the notice.
(d) Unless the lien has been secured, the demand may not be made
after expiration of the time within which the claimant may secure
the lien for the claim.
Acts 1983, 68th Leg., p. 3544, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.084. OWNER'S LIABILITY. (a) Except for the amount
required to be retained under Subchapter E, the owner is not
liable for any amount paid to the original contractor before the
owner is authorized to withhold funds under this subchapter.
(b) If the owner has received the notices required by Subchapter
C or K, if the lien has been secured, and if the claim has been
reduced to final judgment, the owner is liable and the owner's
property is subject to a claim for any money paid to the original
contractor after the owner was authorized to withhold funds under
this subchapter. The owner is liable for that amount in addition
to any amount for which he is liable under Subchapter E.
Acts 1983, 68th Leg., p. 3545, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 12, eff.
Sept. 1, 1997.
Sec. 53.085. AFFIDAVIT REQUIRED. (a) Any person who furnishes
labor or materials for the construction of improvements on real
property shall, if requested and as a condition of payment for
such labor or materials, provide to the requesting party, or the
party's agent, an affidavit stating that the person has paid each
of the person's subcontractors, laborers, or materialmen in full
for all labor and materials provided to the person for the
construction. In the event, however, that the person has not paid
each of the person's subcontractors, laborers, or materialmen in
full, the person shall state in the affidavit the amount owed and
the name and, if known, the address and telephone number of each
subcontractor, laborer, or materialman to whom the payment is
owed.
(b) The seller of any real property shall, upon request by the
purchaser or the purchaser's agent prior to closing of the
purchase of the real property, provide to the purchaser or the
purchaser's agent, a written affidavit stating that the seller
has paid each of the seller's contractors, laborers, or
materialmen in full for all labor and materials provided to the
seller through the date specified in the affidavit for any
construction of improvements on the real property and that the
seller is not indebted to any person, firm, or corporation by
reason of any such construction through the date specified in the
affidavit. In the event that the seller has not paid each of the
seller's contractors, laborers, or materialmen in full for labor
and material provided through the date specified in the
affidavit, the seller shall state in the affidavit the amount
owed and the name and, if known, the address and telephone number
of each contractor, laborer, or materialman to whom the payment
is owed.
(c) The affidavit may include:
(1) a waiver or release of lien rights by the affiant that is
conditioned on the receipt of actual payment or collection of
funds when payment is made by check or draft;
(2) a warranty or representation that certain bills or classes
of bills will be paid by the affiant from funds paid in reliance
on the affidavit; and
(3) an indemnification by the affiant for any loss or expense
resulting from false or incorrect information in the affidavit.
(d) A person, including a seller, commits an offense if the
person intentionally, knowingly, or recklessly makes a false or
misleading statement in an affidavit under this section. An
offense under this section is a misdemeanor. A person adjudged
guilty of an offense under this section shall be punished by a
fine not to exceed $4,000 or confinement in jail for a term not
to exceed one year or both a fine and confinement. A person may
not receive community supervision for the offense.
(e) A person signing an affidavit under this section is
personally liable for any loss or damage resulting from any false
or incorrect information in the affidavit.
Added by Acts 1987, 70th Leg., ch. 578, Sec. 1, eff. Aug. 31,
1987. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 14, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 13, eff. Sept.
1, 1997.
SUBCHAPTER E. REQUIRED RETAINAGE FOR BENEFIT OF LIEN CLAIMANTS
Sec. 53.101. REQUIRED RETAINAGE. (a) During the progress of
work under an original contract for which a mechanic's lien may
be claimed and for 30 days after the work is completed, the owner
shall retain:
(1) 10 percent of the contract price of the work to the owner;
or
(2) 10 percent of the value of the work, measured by the
proportion that the work done bears to the work to be done, using
the contract price or, if there is no contract price, using the
reasonable value of the completed work.
(b) In this section, "owner" includes the owner's agent,
trustee, or receiver.
Acts 1983, 68th Leg., p. 3545, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 15, eff.
Sept. 1, 1989.
Sec. 53.102. PAYMENT SECURED BY RETAINAGE. The retained funds
secure the payment of artisans and mechanics who perform labor or
service and the payment of other persons who furnish material,
material and labor, or specially fabricated material for any
contractor, subcontractor, agent, or receiver in the performance
of the work.
Acts 1983, 68th Leg., p. 3545, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.103. LIEN ON RETAINED FUNDS. A claimant has a lien on
the retained funds if the claimant:
(1) sends the notices required by this chapter in the time and
manner required; and
(2) files an affidavit claiming a lien not later than the 30th
day after the earlier of the date:
(A) the work is completed;
(B) the original contract is terminated; or
(C) the original contractor abandons performance under the
original contract.
Acts 1983, 68th Leg., p. 3545, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Amended by:
Acts 2005, 79th Leg., Ch.
1003, Sec. 1, eff. September 1, 2005.
Sec. 53.104. PREFERENCES. (a) Individual artisans and
mechanics are entitled to a preference to the retained funds and
shall share proportionately to the extent of their claims for
wages and fringe benefits earned.
(b) After payment of artisans and mechanics who are entitled to
a preference under Subsection (a), other participating claimants
share proportionately in the balance of the retained funds.
Acts 1983, 68th Leg., p. 3546, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 16, eff.
Sept. 1, 1989.
Sec. 53.105. OWNER'S LIABILITY FOR FAILURE TO RETAIN. (a) If
the owner fails or refuses to comply with this subchapter, the
claimants complying with this chapter have a lien, at least to
the extent of the amount that should have been retained from the
original contract under which they are claiming, against the
house, building, structure, fixture, or improvement and all of
its properties and against the lot or lots of land necessarily
connected.
(b) The claimants share the lien proportionately in accordance
with the preference provided by Section 53.104.
Acts 1983, 68th Leg., p. 3546, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 2, Sec. 13.02, eff.
Aug. 28, 1989; Acts 1989, 71st Leg., ch. 1138, Sec. 17, eff.
Sept. 1, 1989.
Sec. 53.106. AFFIDAVIT OF COMPLETION. (a) An owner may file
with the county clerk of the county in which the property is
located an affidavit of completion. The affidavit must contain:
(1) the name and address of the owner;
(2) the name and address of the original contractor;
(3) a description, legally sufficient for identification, of the
real property on which the improvements are located;
(4) a description of the improvements furnished under the
original contract;
(5) a statement that the improvements under the original
contract have been completed and the date of completion; and
(6) a conspicuous statement that a claimant may not have a lien
on retained funds unless the claimant files the affidavit
claiming a lien not later than the 30th day after the date of
completion.
(b) A copy of the affidavit must be sent by certified or
registered mail to the original contractor not later than the
date the affidavit is filed and to each claimant who sends a
notice of lien liability to the owner under Section 53.056,
53.057, 53.058, 53.252, or 53.253 not later than the date the
affidavit is filed or the 10th day after the date the owner
receives the notice of lien liability, whichever is later.
(c) A copy of the affidavit must also be sent to each person who
furnishes labor or materials for the property and who furnishes
the owner with a written request for the copy. The owner must
furnish the copy to the person not later than the date the
affidavit is filed or the 10th day after the date the request is
received, whichever is later.
(d) Except as provided by this subsection, an affidavit filed
under this section on or before the 10th day after the date of
completion of the improvements is prima facie evidence of the
date the work under the original contract is completed for
purposes of this subchapter. If the affidavit is filed after the
10th day after the date of completion, the date of completion for
purposes of this subchapter is the date the affidavit is filed.
This subsection does not apply to a person to whom the affidavit
was not sent as required by this section.
(e) Repealed by Acts 1999, 76th Leg., ch. 889, Sec. 12, eff.
Sept. 1, 1999.
Added by Acts 1989, 71st Leg., ch. 1138, Sec. 18, eff. Sept. 1,
1989. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 14, eff.
Sept. 1, 1997; Acts 1999, 76th Leg., ch. 889, Sec. 12, eff. Sept.
1, 1999.
Sec. 53.107. NOTICE RELATING TO TERMINATION OF WORK OR
ABANDONMENT OF PERFORMANCE BY ORIGINAL CONTRACTOR OR OWNER. (a)
Not later than the 10th day after the date an original contract
is terminated or the original contractor abandons performance
under the original contract, the owner shall give notice to each
subcontractor who, before the date of termination or abandonment,
has:
(1) given notice to the owner as provided by Section 53.056,
53.057, or 53.058; or
(2) sent to the owner by certified or registered mail a written
request for notice of termination or abandonment.
(b) The notice must contain:
(1) the name and address of the owner;
(2) the name and address of the original contractor;
(3) a description, legally sufficient for identification, of the
real property on which the improvements are located;
(4) a general description of the improvements agreed to be
furnished under the original contract;
(5) a statement that the original contract has been terminated
or that performance under the contract has been abandoned;
(6) the date of the termination or abandonment; and
(7) a conspicuous statement that a claimant may not have a lien
on the retained funds unless the claimant files an affidavit
claiming a lien not later than the 30th day after the date of the
termination or abandonment.
(c) A notice sent in compliance with this section on or before
the 10th day after the date of termination or abandonment is
prima facie evidence of the date the original contract was
terminated or work was abandoned for purposes of this subchapter.
(d) A subcontractor who fails to file a lien affidavit in the
time prescribed by Section 53.103(2) has a lien to the extent
authorized under this subchapter if:
(1) the subcontractor otherwise complies with this chapter; and
(2) the owner did not provide the subcontractor notice as
required by this section.
(e) This section does not apply to a residential construction
project.
Added by Acts 2005, 79th Leg., Ch.
1003, Sec. 2, eff. September 1, 2005.
SUBCHAPTER F. PRIORITIES AND PREFERENCES
Sec. 53.121. PREFERENCE OVER OTHER CREDITORS. All
subcontractors, laborers, and materialmen who have a mechanic's
lien have preference over other creditors of the original
contractor.
Acts 1983, 68th Leg., p. 3546, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.122. EQUALITY OF MECHANIC'S LIENS. (a) Except as
provided by Subchapter E and Section 53.124(e), perfected
mechanic's liens are on equal footing without reference to the
date of filing the affidavit claiming the lien.
(b) If the proceeds of a foreclosure sale of property are
insufficient to discharge all mechanic's liens against the
property, the proceeds shall be paid pro rata on the perfected
mechanic's liens on which suit is brought.
(c) This chapter does not affect the contract between the owner
and the original contractor as to the amount, manner, or time of
payment of the contract price.
Acts 1983, 68th Leg., p. 3546, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1995, 74th Leg., ch. 851, Sec. 4, eff.
Sept. 1, 1995.
Sec. 53.123. PRIORITY OF MECHANIC'S LIEN OVER OTHER LIENS. (a)
Except as provided by this section, a mechanic's lien attaches to
the house, building, improvements, or railroad property in
preference to any prior lien, encumbrance, or mortgage on the
land on which it is located, and the person enforcing the lien
may have the house, building, improvement, or any piece of the
railroad property sold separately.
(b) The mechanic's lien does not affect any lien, encumbrance,
or mortgage on the land or improvement at the time of the
inception of the mechanic's lien, and the holder of the lien,
encumbrance, or mortgage need not be made a party to a suit to
foreclose the mechanic's lien.
Acts 1983, 68th Leg., p. 3547, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.124. INCEPTION OF MECHANIC'S LIEN. (a) Except as
provided by Subsection (e), for purposes of Section 53.123, the
time of inception of a mechanic's lien is the commencement of
construction of improvements or delivery of materials to the land
on which the improvements are to be located and on which the
materials are to be used.
(b) The construction or materials under Subsection (a) must be
visible from inspection of the land on which the improvements are
being made.
(c) An owner and original contractor may jointly file an
affidavit of commencement with the county clerk of the county in
which the land is located not later than the 30th day after the
date of actual commencement of construction of the improvements
or delivery of materials to the land. The affidavit must contain:
(1) the name and address of the owner;
(2) the name and address of each original contractor, known at
the time to the owner, that is furnishing labor, service, or
materials for the construction of the improvements;
(3) a description, legally sufficient for identification, of the
property being improved;
(4) the date the work actually commenced; and
(5) a general description of the improvement.
(d) An affidavit filed in compliance with this section is prima
facie evidence of the date of the commencement of the improvement
described in the affidavit. The time of inception of a mechanic's
lien arising from work described in an affidavit of commencement
is the date of commencement of the work stated in the affidavit.
(e) The time of inception of a lien that is created under
Section 53.021(c), (d), or (e) is the date of recording of an
affidavit of lien under Section 53.052. The priority of a lien
claimed by a person entitled to a lien under Section 53.021(c),
(d), or (e) with respect to other mechanic's liens is determined
by the date of recording. A lien created under Section 53.021(c),
(d), or (e) is not valid or enforceable against a grantee or
purchaser who acquires an interest in the real property before
the time of inception of the lien.
Acts 1983, 68th Leg., p. 3547, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 19, eff.
Sept. 1, 1989; Acts 1995, 74th Leg., ch. 851, Sec. 5, eff. Sept.
1, 1995; Acts 1999, 76th Leg., ch. 896, Sec. 2, eff. Sept. 1,
1999; Acts 2003, 78th Leg., ch. 410, Sec. 2, eff. Sept. 1, 2003.
SUBCHAPTER G. RELEASE AND FORECLOSURE; ACTION ON CLAIM
Sec. 53.151. ENFORCEMENT OF REMEDIES AGAINST MONEY DUE ORIGINAL
CONTRACTOR OR SUBCONTRACTOR. (a) A creditor of an original
contractor may not collect, enforce a security interest against,
garnish, or levy execution on the money due the original
contractor or the contractor's surety from the owner, and a
creditor of a subcontractor may not collect, enforce a security
interest against, garnish, or levy execution on the money due the
subcontractor, to the prejudice of the subcontractors, mechanics,
laborers, materialmen, or their sureties.
(b) A surety issuing a payment bond or performance bond in
connection with the improvements has a priority claim over other
creditors of its principal to contract funds to the extent of any
loss it suffers or incurs. That priority does not excuse the
surety from paying any obligations that it may have under its
payment bonds.
Acts 1983, 68th Leg., p. 3548, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 20, eff.
Sept. 1, 1989.
Sec. 53.152. RELEASE OF CLAIM OR LIEN. (a) When a debt for
labor or materials is satisfied or paid by collected funds, the
person who furnished the labor or materials shall, not later than
the 10th day after the date of receipt of a written request,
furnish to the requesting person a release of the indebtedness
and any lien claimed, to the extent of the indebtedness paid. An
owner, the original contractor, or any person making the payment
may request the release.
(b) A release of lien must be in a form that would permit it to
be filed of record.
Acts 1983, 68th Leg., p. 3548, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 21, eff.
Sept. 1, 1989.
Sec. 53.153. DEFENSE OF ACTIONS. (a) If an affidavit claiming
a mechanic's lien is filed by a person other than the original
contractor, the original contractor shall defend at his own
expense a suit brought on the claim.
(b) If the suit results in judgment on the lien against the
owner or the owner's property, the owner is entitled to deduct
the amount of the judgment and costs from any amount due the
original contractor. If the owner has settled with the original
contractor in full, the owner is entitled to recover from the
original contractor any amount paid for which the original
contractor was originally liable.
Acts 1983, 68th Leg., p. 3548, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.154. FORECLOSURE. A mechanic's lien may be foreclosed
only on judgment of a court of competent jurisdiction foreclosing
the lien and ordering the sale of the property subject to the
lien.
Acts 1983, 68th Leg., p. 3549, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.155. TRANSFER OF PROPERTY SOLD. If the house, building,
improvement, or any piece of railroad property is sold
separately, the officer making the sale shall place the purchaser
in possession. The purchaser is entitled to a reasonable time
after the date of purchase within which to remove the purchased
property.
Acts 1983, 68th Leg., p. 3549, ch. 576, Sec. 1, eff. Jan. 1,
1984.
Sec. 53.156. COSTS AND ATTORNEY'S FEES. In any proceeding to
foreclose a lien or to enforce a claim against a bond issued
under Subchapter H, I, or J or in any proceeding to declare that
any lien or claim is invalid or unenforceable in whole or in
part, the court may award costs and reasonable attorney's fees as
are equitable and just.
Added by Acts 1984, 68th Leg., 2nd C.S., ch. 18, Sec. 4(a), eff.
Oct. 2, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 22,
eff. Sept. 1, 1989.
Sec. 53.157. DISCHARGE OF LIEN. A mechanic's lien or affidavit
claiming a mechanic's lien filed under Section 53.052 may be
discharged of record by:
(1) recording a lien release signed by the claimant under
Section 53.152;
(2) failing to institute suit to foreclose the lien in the
county in which the property is located within the period
prescribed by Section 53.158, 53.175, or 53.208;
(3) recording the original or certified copy of a final judgment
or decree of a court of competent jurisdiction providing for the
discharge;
(4) filing the bond and notice in compliance with Subchapter H;
(5) filing the bond in compliance with Subchapter I; or
(6) recording a certified copy of the order removing the lien
under Section 53.160 and a certificate from the clerk of the
court that states that no bond or deposit as described by Section
53.161 was filed by the claimant within 30 days after the date
the order was entered.
Added by Acts 1989, 71st Leg., ch. 1138, Sec. 23, eff. Sept. 1,
1989. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 15, eff.
Sept. 1, 1997.
Sec. 53.158. PERIOD FOR BRINGING SUIT TO FORECLOSE LIEN. (a)
Except as provided by Subsection (b), suit must be brought to
foreclose the lien within two years after the last day a claimant
may file the lien affidavit under Section 53.052 or within one
year after completion, termination, or abandonment of the work
under the original contract under which the lien is claimed,
whichever is later.
(b) For a claim arising from a residential construction project,
suit must be brought to foreclose the lien within one year after
the last day a claimant may file a lien affidavit under Section
53.052 or within one year after completion, termination, or
abandonment of the work under the original contract under which
the lien is claimed, whichever is later.
Added by Acts 1989, 71st Leg., ch. 1138, Sec. 23, eff. Sept. 1,
1989. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 16, eff.
Sept. 1, 1997; Acts 1999, 76th Leg., ch. 889, Sec. 4, eff. Sept.
1, 1999.
Sec. 53.159. OBLIGATION TO FURNISH INFORMATION. (a) An owner,
on written request, shall furnish the following information
within a reasonable time, but not later than the 10th day after
the date the request is received, to any person furnishing labor
or materials for the project:
(1) a description of the real property being improved legally
sufficient to identify it;
(2) whether there is a surety bond and if so, the name and last
known address of the surety and a copy of the bond; and
(3) whether there are any prior recorded liens or security
interests on the real property being improved and if so, the name
and address of the person having the lien or security interest.
(b) An original contractor, on written request by a person who
furnished work under the original contract, shall furnish to the
person the following information within a reasonable time, but
not later than the 10th day after the date the request is
received:
(1) the name and last known address of the person to whom the
original contractor furnished labor or materials for the
construction project; and
(2) whether the original contractor has furnished or has been
furnished a payment bond for any of the work on the construction
project and if so, the name and last known address of the surety
and a copy of the bond.
(c) A subcontractor, on written request by an owner of the
property being improved, the original contractor, a surety on a
bond covering the original contract, or any person furnishing
work under the subcontract, shall furnish to the person the
following information within a reasonable time, but not later
than the 10th day after the date the request is received:
(1) the name and last known address of each person from whom the
subcontractor purchased labor or materials for the construction
project, other than those materials that were furnished to the
project from the subcontractor's inventory;
(2) the name and last known address of each person to whom the
subcontractor furnished labor or materials for the construction
project; and
(3) whether the subcontractor has furnished or has been
furnished a payment bond for any of the work on the construction
project and if so, the name and last known address of the surety
and a copy of the bond.
(d) Not later than the 30th day after the date a written request
is received from the owner, the contractor under whom a claim of
lien or under whom a bond is made, or a surety on a bond on which
a claim is made, a claimant for a lien or under a bond shall
furnish to the requesting person a copy of any applicable written
agreement, purchase order, or contract and any billing,
statement, or payment request of the claimant reflecting the
amount claimed and the work performed by the claimant for which
the claim is made. If requested, the claimant shall provide the
estimated amount due for each calendar month in which the
claimant has performed labor or furnished materials.
(e) If a person from whom information is requested does not have
a direct contractual relationship on the project with the person
requesting the information, the person from whom information is
requested, other than a claimant requested to furnish information
under Subsection (d), may require payment of the actual costs,
not to exceed $25, in furnishing the requested information.
(f) A person, other than a claimant requested to furnish
information under Subsection (d), who fails to furnish
information as required by this section is liable to the
requesting person for that person's reasonable and necessary
costs incurred in procuring the requested information.
Added by Acts 1989, 71st Leg., ch. 1138, Sec. 23, eff. Sept. 1,
1989.
Sec. 53.160. SUMMARY MOTION TO REMOVE INVALID OR UNENFORCEABLE
LIEN. (a) In a suit brought to foreclose a lien or to declare a
claim or lien invalid or unenforceable, a party objecting to the
validity or enforceability of the claim or lien may file a motion
to remove the claim or lien. The motion must be verified and
state the legal and factual basis for objecting to the validity
or enforceability of the claim or lien. The motion may be
accompanied by supporting affidavits.
(b) The grounds for objecting to the validity or enforceability
of the claim or lien for purposes of the motion are limited to
the following:
(1) notice of claim was not furnished to the owner or original
contractor as required by Section 53.056, 53.057, 53.058, 53.252,
or 53.253;
(2) an affidavit claiming a lien failed to comply with Section
53.054 or was not filed as required by Section 53.052;
(3) notice of the filed affidavit was not furnished to the owner
or original contractor as required by Section 53.055;
(4) the owner complied with the requirements of Section 53.101
and paid the retainage and all other funds owed to the original
contractor before:
(A) the claimant perfected the lien claim; and
(B) the owner received a notice of the claim as required by this
chapter;
(5) all funds subject to the notice of a claim to the owner and
the perfection of a claim against the statutory retainage have
been deposited in the registry of the court and the owner has no
additional liability to the claimant;
(6) when the lien affidavit was filed on homestead property:
(A) no contract was executed or filed as required by Section
53.254;
(B) the affidavit claiming a lien failed to contain the notice
as required by Section 53.254; or
(C) the notice of the claim failed to include the statement
required by Section 53.254; and
(7) the claimant executed a valid and enforceable waiver or
release of the claim or lien claimed in the affidavit.
(c) The claimant is not required to file a response. The
claimant and any other party that has appeared in the proceeding
must be notified by at least 21 days before the date of the
hearing on the motion. A motion may not be heard before the 21st
day after the date the claimant answers or appears in the
proceeding.
(d) At the hearing on the motion, the burden is on:
(1) the claimant to prove that the notice of claim and affidavit
of lien were furnished to the owner and original contractor as
required by this chapter; and
(2) the movant to establish that the lien should be removed for
any other ground authorized by this section.
(e) The court shall promptly determine a motion to remove a
claim or lien under this section. If the court determines that
the movant is not entitled to remove the lien, the court shall
enter an order denying the motion. If the court determines that
the movant is entitled to remove the lien, the court shall enter
an order removing the lien claimed in the lien affidavit. A party
to the proceeding may not file an interlocutory appeal from the
court's order.
(f) Any admissible evidence offered at the hearing may be
admitted in the trial of the case. The court's order under
Subsection (e) is not admissible as evidence in determining the
validity and enforceability of the claim or lien.
Added by Acts 1997, 75th Leg., ch. 526, Sec. 17, eff. Sept. 1,
1997.
Sec. 53.161. BOND REQUIREMENTS AFTER ORDER TO REMOVE. (a) In
the order removing a lien, the court shall set the amount of
security that the claimant may provide in order to stay the
removal of the claim or lien. The sum must be an amount that the
court determines is a reasonable estimate of the costs and
attorney's fees the movant is likely to incur in the proceeding
to determine the validity or enforceability of the lien. The sum
may not exceed the amount of the lien claim.
(b) The court shall stay the order removing the lien if the
claimant files a bond or a deposit in lieu of a bond in the
amount set in the order with the clerk of the court not later
than the 30th day after the date the order is entered by the
court unless, for good cause, the court orders a later date for
filing the bond or the deposit in lieu of a bond. If the court
fails to set the amount of the security required, the amount
required is the amount of the lien claim.
(c) The bond must be:
(1) executed by a corporate surety authorized to do business in
this state and licensed by this state to execute bonds as surety;
and
(2) conditioned on the claimant's payment of any final judgment
rendered against the claimant in the proceeding for attorney's
fees and costs to the movant under Section 53.156.
(d) In lieu of filing a bond, the claimant may deposit in the
amount set by the court for the surety bond:
(1) cash;
(2) a negotiable obligation of the federal government or a
federal agency; or
(3) a negotiable obligation of a financial institution chartered
by the federal or state government that is insured by the federal
government or a federal agency.
(e) A deposit made under Subsection (d) must be conditioned in
the same manner as a surety bond. Any interest accrued on the
deposit amount is a part of the deposit.
(f) If the claimant fails to file the bond or the deposit in
lieu of the bond in compliance with this section, the owner may
file:
(1) a certified copy of the order; and
(2) a certificate from the clerk of the court stating that:
(A) no bond or deposit in lieu of the bond was filed within 30
days after the date the order was entered by the court; and
(B) no order staying the order to remove the lien was entered by
the court.
(g) The claim or lien is removed and extinguished as to a
creditor or subsequent purchaser for valuable consideration who
obtains an interest in the property after the certified copy of
the order and certificate of the clerk of the court are filed
with the county clerk. The removal of the lien does not
constitute a release of the liability of the owner, if any, to
the claimant.
Added by Acts 1997, 75th Leg., ch. 526, Sec. 17, eff. Sept. 1,
1997.
Sec. 53.162. REVIVAL OF REMOVED LIEN. (a) If an order removing
the lien is not stayed as provided by Section 53.161 and the
claimant later obtains a final judgment in the suit establishing
the validity and ordering the foreclosure of the lien, the
claimant may file a certified copy of the final judgment with the
county clerk.
(b) The filed judgment revives the lien, and the claimant may
foreclose the lien.
(c) A lien revived under this section is void as to a creditor
or subsequent purchaser for valuable consideration who obtained
an interest in the property:
(1) after the order removing the lien and the certificate from
the clerk of the court was filed with the county clerk; and
(2) before the final judgment reviving the lien was filed with
the county clerk.
Added by Acts 1997, 75th Leg., ch. 526, Sec. 17, eff. Sept. 1,
1997.
SUBCHAPTER H. BOND TO INDEMNIFY AGAINST LIEN
Sec. 53.171. BOND. (a) If a lien, other than a lien granted by
the owner in a written contract, is fixed or is attempted to be
fixed by a recorded instrument under this chapter, any person may
file a bond to indemnify against the lien.
(b) The bond shall be filed with the county clerk of the county
in which the property subject to the lien is located.
(c) A mechanic's lien claim against an owner's property is
discharged after:
(1) a bond that complies with Section 53.172 is filed;
(2) the notice of the bond is issued as provided by Section
53.173; and
(3) the bond and notice are recorded as provided by Section
53.174.
Acts 1983, 68th Leg., p. 3549, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 24, 39(1),
eff. Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 18, eff.
Sept. 1, 1997.
Sec. 53.172. BOND REQUIREMENTS. The bond must:
(1) describe the property on which the liens are claimed;
(2) refer to each lien claimed in a manner sufficient to
identify it;
(3) be in an amount that is double the amount of the liens
referred to in the bond unless the total amount claimed in the
liens exceeds $40,000, in which case the bond must be in an
amount that is the greater of 1-1/2 times the amount of the liens
or the sum of $40,000 and the amount of the liens;
(4) be payable to the parties claiming the liens;
(5) be executed by:
(A) the party filing the bond as principal; and
(B) a corporate surety authorized and admitted to do business
under the law in this state and licensed by this state to execute
the bond as surety, subject to Section 1, Chapter 87, Acts of the
56th Legislature, Regular Session, 1959 (Article 7.19-1, Vernon's
Texas Insurance Code); and
(6) be conditioned substantially that the principal and sureties
will pay to the named obligees or to their assignees the amount
that the named obligees would have been entitled to recover if
their claims had been proved to be valid and enforceable liens on
the property.
Acts 1983, 68th Leg., p. 3549, ch. 576, Sec. 1, eff. Jan. 1,
1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 25, eff.
Sept. 1, 1989; Acts 1997, 75th Leg., ch. 1132, Sec. 2, eff. Sept.
1, 1997.
Sec. 53.173. NOTICE OF BOND. (a) After the bond is filed, the
county clerk shall issue notice of the bond to all named
obli