departments, divisions, and agencies concerned with surface mine reclamation and the health andsafety of underground miners; and
(ii) the operations will result in improved resource recovery, abatement of waterpollution, or elimination of hazards to the health and safety of the public.
(m) Design, locate, construct, operate, maintain, enlarge, modify, and remove orabandon, in accordance with the standards and criteria developed pursuant to the division's rules,all existing and new coal mine waste piles consisting of mine wastes, tailings, coal processingwastes, or other liquid and solid wastes, and used either temporarily or permanently as dams orembankments.
(n) Insure that all debris, acid-forming materials, toxic materials, or materialsconstituting a fire hazard are treated or buried and compacted or otherwise disposed of in amanner designed to prevent contamination of ground or surface waters and that contingencyplans are developed to prevent sustained combustion.
(o) Insure that explosives are used only in accordance with existing state and federal lawand the rules adopted by the board, which shall include provisions to:
(i) provide adequate advance written notice to local governments and residents whomight be affected by the use of the explosives by:
(A) publication of the planned blasting schedule:
(I) in a newspaper of general circulation in the locality; and
(II) as required in Section 45-1-101; and
(B) mailing a copy of the proposed blasting schedule to every resident living within 1/2mile of the proposed blasting site and by providing daily notice to resident/occupiers in theseareas prior to any blasting;
(ii) maintain for a period of at least three years and make available for public inspectionupon request a log detailing the location of the blasts, the pattern and depth of the drill holes, theamount of explosives used per hole, and the order and length of delay in the blasts;
(iii) limit the type of explosives and detonating equipment, the size, the timing andfrequency of blasts based upon the physical conditions of the site so as to prevent injury topersons, damage to public and private property outside the permit area, adverse impacts on anyunderground mine, and change in the course, channel, or availability of ground or surface wateroutside the permit area;
(iv) require that all blasting operations be conducted by trained and competent persons,and to implement this requirement, the division shall promulgate rules requiring the training,examination, and certification of persons engaging in or directly responsible for blasting or theuse of explosives in surface and coal mining operations; and
(v) provide that upon the request of a resident or owner of a man-made dwelling orstructure within 1/2 mile of any portion of the permitted area, the applicant or permittee shallconduct a preblasting survey of the structures and submit the survey to the division and a copy tothe resident or owner making the request, the area of which survey shall be decided by thedivision and shall include such provisions as promulgated.
(p) Insure that all reclamation efforts proceed in an environmentally sound manner and ascontemporaneously as practicable with the surface coal mining operations; but where theapplicant proposes to combine surface mining operations with underground mining operations toassure maximum practical recovery of the mineral resources, the division may grant a variancefor specific areas within the reclamation plan from the requirement that reclamation efforts
proceed as contemporaneously as practicable to permit underground operations prior toreclamation:
(i) if the division finds in writing that:
(A) the applicant has presented, as part of the permit application, specific, feasible plansfor the proposed underground mining operations;
(B) the proposed underground mining operations are necessary or desirable to assuremaximum practical recovery of the mineral resource and will avoid multiple disturbance of thesurface;
(C) the applicant has satisfactorily demonstrated that the plan for the undergroundmining operations conforms to requirements for underground mining in the jurisdiction and thatpermits necessary for the underground mining operations have been issued by the appropriateauthority;
(D) the areas proposed for the variance have been shown by the applicant to be necessaryfor the implementing of the proposed underground mining operations;
(E) no substantial adverse environmental damage, either onsite or offsite, will result fromthe delay in completion of reclamation as required by this chapter; and
(F) provisions for the offsite storage of spoil will comply with Subsection (2)(v);
(ii) if the board has adopted specific rules to govern the granting of the variances inaccordance with the provisions of this Subsection (2)(p) and has imposed such additionalrequirements as considered necessary;
(iii) if variances granted under this Subsection (2)(p) are to be reviewed by the divisionnot more than three years from the date of issuance of the permit; and
(iv) if liability under the bond filed by the applicant with the division pursuant to Section40-10-15 shall be for the duration of the underground mining operations and until therequirements of this Subsection (2) and Section 40-10-16 have been fully complied with.
(q) Insure that the construction, maintenance, and postmining conditions of access roadsinto and across the site of operations will control or prevent erosion and siltation, pollution ofwater, damage to fish or wildlife or their habitat, or public or private property.
(r) Refrain from the construction of roads or other access ways up a stream bed ordrainage channel or in such proximity to the channel so as to seriously alter the normal flow ofwater.
(s) Establish on the regraded areas and all other lands affected, a diverse, effective, andpermanent vegetative cover of the same seasonal variety native to the area of land to be affectedand capable of self-regeneration and plant succession at least equal in extent of cover to thenatural vegetation of the area; except that introduced species may be used in the revegetationprocess where desirable and necessary to achieve the approved postmining land use plan.
(t) (i) Assume the responsibility for successful revegetation, as required by Subsection(2)(s), for a period of five full years after the last year of augmented seeding, fertilizing,irrigation, or other work in order to assure compliance with Subsection (2)(s), except in thoseareas or regions of the state where the annual average precipitation is 26 inches or less, then theoperator's assumption of responsibility and liability will extend for a period of 10 full years afterthe last year of augmented seeding, fertilizing, irrigation, or other work; but when the divisionapproves a long-term intensive agricultural postmining land use, the applicable five or ten-yearperiod of responsibility for revegetation shall commence at the date of initial planting for thislong-term intensive, agricultural postmining land use, except when the division issues a written
finding approving a long-term, intensive, agricultural postmining land use, as part of the miningand reclamation plan, the division may grant exception to the provisions of Subsection (2)(s);and
(ii) on lands eligible for remining, assume the responsibility for successful revegetationfor a period of two full years after the last year of augmented seeding, fertilizing, irrigation, orother work in order to assure compliance with the applicable standards, except in areas of thestate where the average annual precipitation is 26 inches or less, assume the responsibility forsuccessful revegetation for a period of five full years after the last year of augmented seeding,fertilizing, irrigation, or other work in order to assure compliance with the applicable standards.
(u) Protect offsite areas from slides or damage occurring during the surface coal miningand reclamation operations and not deposit spoil material or locate any part of the operations orwaste accumulations outside the permit area.
(v) Place all excess spoil material resulting from coal surface mining and reclamationactivities in a manner that:
(i) spoil is transported and placed in a controlled manner in position for concurrentcompaction and in a way to assure mass stability and to prevent mass movement;
(ii) the areas of disposal are within the bonded permit areas and all organic matter shallbe removed immediately prior to spoil placement;
(iii) appropriate surface and internal drainage systems and diversion ditches are used soas to prevent spoil erosion and movement;
(iv) the disposal area does not contain springs, natural water courses, or wet weatherseeps unless lateral drains are constructed from the wet areas to the main underdrains in a mannerthat filtration of the water into the spoil pile will be prevented;
(v) if placed on a slope, the spoil is placed upon the most moderate slope among thoseupon which, in the judgment of the division, the spoil could be placed in compliance with all therequirements of this chapter and shall be placed, where possible, upon or above a natural terrace,bench, or berm, if this placement provides additional stability and prevents mass movement;
(vi) where the toe of the spoil rests on a downslope, a rock toe buttress of sufficient sizeto prevent mass movement, is constructed;
(vii) the final configuration is compatible with the natural drainage pattern andsurroundings and suitable for intended uses;
(viii) design of the spoil disposal area is certified by a qualified professional engineer,and to implement this requirement, the division shall promulgate rules regarding the certificationof engineers in the area of spoil disposal design; and
(ix) all other provisions of this chapter are met.
(w) Meet such other criteria as are necessary to achieve reclamation in accordance withthe purposes of this chapter, taking into consideration the physical, climatological, and othercharacteristics of the site.
(x) To the extent possible, using the best technology currently available, minimizedisturbances and adverse impacts of the operation on fish, wildlife, and related environmentalvalues, and achieve enhancement of these resources where practicable.
(y) Provide for an undisturbed natural barrier beginning at the elevation of the lowestcoal seam to be mined and extending from the outslope for the distance as the division shalldetermine shall be retained in place as a barrier to slides and erosion.
(3) (a) Where an applicant meets the requirements of Subsections (3)(b) and (c), a permit
without regard to the requirement to restore to approximate original contour provided inSubsections (2)(c), (4)(b), and (4)(c) may be granted for the surface mining of coal where themining operation will remove an entire coal seam or seams running through the upper fraction ofa mountain, ridge, or hill (except as provided in this Subsection (3)) by removing all of theoverburden and creating a level plateau or a gently rolling contour with no highwalls remaining,and capable of supporting postmining uses in accord with the requirements of this Subsection(3).
(b) In cases where an industrial, commercial, agricultural, residential, or public facility(including recreational facilities) use is proposed for the postmining use of the affected land, thedivision may grant a permit for a surface mining operation of the nature described in Subsection(3)(a) pursuant to procedures and criteria set forth in the rules, including:
(i) the applicant's presentation of specific plans for the proposed postmining land usewhich meet criteria concerning the type of use proposed;
(ii) the applicant's demonstration that the proposed use would be consistent with adjacentland uses and existing state and local land use plans and programs and with other requirements ofthis chapter; and
(iii) procedures whereby the division provides the governing body of the unit ofgeneral-purpose government in which the land is located and any state or federal agency whichthe division, in its discretion, determines to have an interest in the proposed use, an opportunityof not more than 60 days to review and comment on the proposed use.
(c) All permits granted under the provisions of this Subsection (3) shall be reviewed notmore than three years from the date of issuance of the permit, unless the applicant affirmativelydemonstrates that the proposed development is proceeding in accordance with the terms of theapproved schedule and reclamation plan.
(4) The following performance standards shall be applicable to steep-slope surface coalmining and shall be in addition to those general performance standards required by this section;but the provisions of this Subsection (4) shall not apply to those situations in which an operator ismining on flat or gently rolling terrain, on which an occasional steep slope is encounteredthrough which the mining operation is to proceed, leaving a plain or predominantly flat area orwhere an operator is in compliance with provisions of Subsection (3):
(a) Insure that when performing surface coal mining on steep slopes, no debris,abandoned or disabled equipment, spoil material, or waste mineral matter be placed on thedownslope below the bench or mining cut; but spoil material in excess of that required for thereconstruction of the approximate original contour under the provisions of Subsection (2)(c) orthis Subsection (4) shall be permanently stored pursuant to Subsection 40-10-17(2)(v).
(b) Complete backfilling with spoil material shall be required to cover completely thehighwall and return the site to the appropriate original contour, which material will maintainstability following mining and reclamation.
(c) The operator may not disturb land above the top of the highwall unless the divisionfinds that the disturbance will facilitate compliance with the environmental protection standardsof this section; but the land disturbed above the highwall shall be limited to that amountnecessary to facilitate this compliance.
(d) For the purposes of this Subsection (4), "steep slope" means any slope above 20degrees or such lesser slope as may be defined by the division after consideration of soil, climate,and other characteristics of an area.
Amended by Chapter 309, 2009 General Session
Amended by Chapter 388, 2009 General Session