§ 1626a -   Awards for wastewater treatment plants with a capacity of 250,000 gallons or more per day

§ 1626a. Awards for wastewater treatment plants with a capacity of 250,000 gallons or more per day

(a) Definitions. For the purpose of this section:

(1) "Septage" means the product of an individual or a group septic tank, which is removed from the tank for further processing and disposal.

(2) "Sludge" means the intermediate product of a municipal wastewater treatment plant which receives further processing by the same plant in a manner similar to the processing of septage by the plant.

(3) The project or plant "cost" means the cost of the enlargement or new construction of a wastewater treatment plant which the commissioner of environmental conservation finds is eligible for financial assistance under this section.

(b) Loan eligibility. The proposed enlargement or new construction of a wastewater treatment plant with a total design hydraulic capacity of 250,000 or more gallons per day shall be eligible for a loan for 100 percent of the total project cost, as provided by chapter 120 of Title 24, if the commissioner of environmental conservation finds that:

(1) the proposed plant capacity is necessary to accommodate anticipated municipal growth; and that

(2) the proposed plant capacity will be sufficient to receive, treat and dispose of septage in a quantity equivalent to the ratio of 2,000 gallons or more of such septage per day for each 1,000,000 gallons per day of plant design hydraulic capacity. However, this condition shall not be required if the commissioner finds that such septage treatment capacity by the plant is not needed within the region of the state in which the plant is or will be located.

(c) Additional state assistance eligibility.

(1) Grants. A proposed wastewater treatment plant which is eligible for a loan under subsection (b) of this section, and a wastewater treatment plant with a design hydraulic capacity of 250,000 or more gallons per day which is being refurbished, shall in addition be eligible for a grant of up to 50 percent of the cost of that portion of the plant to be used to treat septage, or septage and sludge in combination, if the commissioner of environmental conservation finds that the proposed plant capacity will be sufficient to receive, treat and dispose of septage alone in a quantity equivalent to the ratio of 4,000 gallons or more of such septage per day for each 1,000,000 gallons per day of plant design hydraulic capacity. The portion of the plant used for processing septage, or septage and sludge in combination, shall include facilities for receiving septage and for the storage, treatment, transfer, and disposal of both septage and sludge.

(2) Loans A proposed wastewater treatment plant which is eligible for a grant under this subsection may receive an interest free loan for the remaining amount of the total project cost, from revolving funds established by chapter 120 of Title 24.

(d) Conditions of additional state assistance. The additional state assistance provided by subsection (c) of this section shall be awarded under the following conditions:

(1) To be eligible for additional assistance, a proposed plant shall be consistent with any solid waste implementation plan adopted pursuant to section 2202a of Title 24, or chapter 117 of Title 24, which is approved by the secretary of natural resources and which addresses septage and sludge management. However, the commissioner of environmental conservation shall not withhold additional assistance because of an absence of an adopted or approved solid waste implementation plan.

(2) Plants eligible for additional assistance shall receive increased funding priority in accordance with rules adopted by the secretary.

(3) A plant receiving additional assistance shall, for the useful life of the facility, maintain its additional processing capacity for use only in receiving and processing septage. Such septage shall be accepted from any Vermont municipality, and shall not be restricted to specific municipalities. The rate or rates charged for acceptance by the plant of septage from sources other than the users for whom the plant is designed primarily to serve, shall be equal to the rate or rates charged the primary users, and shall not subsidize the primary users. The agency shall include these requirements in any permit issued for the construction and operation of the plant, and the requirements shall be enforceable in the manner prescribed for that permit.

(4) Project costs eligible for additional assistance shall include the cost of: land used for the direct disposal of septage and sludge; facilities to receive, store, treat, transfer and dispose of septage and sludge; and facilities to compost or pelletize or otherwise process septage and sludge.

(5) When other state or federal assistance is awarded to a plant eligible for additional assistance under this section, such other assistance shall reduce, first, the loan amount awarded under this section, and secondly, the grant amount awarded under this section. (Added 1993, No. 233 (Adj. Sess.), § 60, eff. June 21, 1994; amended 2007, No. 52, § 42, eff. May 28, 2007.)

Vermont Forms by Issue

Vermont Appeals Forms
Vermont Business Forms
Vermont Court Forms
> Probate
> Civil (District)
> Small Claims
Vermont Divorce Forms
Vermont Family Forms
Vermont Guardianship Forms

Vermont Law

Vermont State Laws
    > Vermont Child Support
    > Vermont Gun Laws
    > Vermont Statutes
Vermont Tax
    > Vermont State Tax
Vermont Agencies
    > Vermont DMV
    > Vermont Federal Credit Union

Vermont Court Map

Tips