Find Laws Find Lawyers Free Legal Forms USA State Laws

WASHINGTON STATUTES AND CODES

80.80.010 - Definitions.

Definitions.

The definitions in this section apply throughout this chapter unless the context clearly requires otherwise.

     (1) "Attorney general" means the Washington state office of the attorney general.

     (2) "Auditor" means: (a) The Washington state auditor's office or its designee for consumer-owned utilities under its jurisdiction; or (b) an independent auditor selected by a consumer-owned utility that is not under the jurisdiction of the state auditor.

     (3) "Average available greenhouse gas emissions output" means the level of greenhouse gas emissions as surveyed and determined by the energy policy division of the department of commerce under RCW 80.80.050.

     (4) "Baseload electric generation" means electric generation from a power plant that is designed and intended to provide electricity at an annualized plant capacity factor of at least sixty percent.

     (5) "Cogeneration facility" means a power plant in which the heat or steam is also used for industrial or commercial heating or cooling purposes and that meets federal energy regulatory commission standards for qualifying facilities under the public utility regulatory policies act of 1978 (16 U.S.C. Sec. 824a-3), as amended.

     (6) "Combined-cycle natural gas thermal electric generation facility" means a power plant that employs a combination of one or more gas turbines and steam turbines in which electricity is produced in the steam turbine from otherwise lost waste heat exiting from one or more of the gas turbines.

     (7) "Commission" means the Washington utilities and transportation commission.

     (8) "Consumer-owned utility" means a municipal utility formed under Title 35 RCW, a public utility district formed under Title 54 RCW, an irrigation district formed under chapter 87.03 RCW, a cooperative formed under chapter 23.86 RCW, a mutual corporation or association formed under chapter 24.06 RCW, or port district within which an industrial district has been established as authorized by Title 53 RCW, that is engaged in the business of distributing electricity to more than one retail electric customer in the state.

     (9) "Department" means the department of ecology.

     (10) "Distributed generation" means electric generation connected to the distribution level of the transmission and distribution grid, which is usually located at or near the intended place of use.

     (11) "Electric utility" means an electrical company or a consumer-owned utility.

     (12) "Electrical company" means a company owned by investors that meets the definition of RCW 80.04.010.

     (13) "Governing board" means the board of directors or legislative authority of a consumer-owned utility.

     (14) "Greenhouse gases" includes carbon dioxide, methane, nitrous oxide, hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride.

     (15) "Long-term financial commitment" means:

     (a) Either a new ownership interest in baseload electric generation or an upgrade to a baseload electric generation facility; or

     (b) A new or renewed contract for baseload electric generation with a term of five or more years for the provision of retail power or wholesale power to end-use customers in this state.

     (16) "Plant capacity factor" means the ratio of the electricity produced during a given time period, measured in kilowatt-hours, to the electricity the unit could have produced if it had been operated at its rated capacity during that period, expressed in kilowatt-hours.

     (17) "Power plant" means a facility for the generation of electricity that is permitted as a single plant by a jurisdiction inside or outside the state.

     (18) "Upgrade" means any modification made for the primary purpose of increasing the electric generation capacity of a baseload electric generation facility. "Upgrade" does not include routine or necessary maintenance, installation of emission control equipment, installation, replacement, or modification of equipment that improves the heat rate of the facility, or installation, replacement, or modification of equipment for the primary purpose of maintaining reliable generation output capability that does not increase the heat input or fuel usage as specified in existing generation air quality permits as of July 22, 2007, but may result in incidental increases in generation capacity.

[2009 c 565 § 54; 2009 c 448 § 1; 2007 c 307 § 2.]

Notes: Reviser's note: This section was amended by 2009 c 448 § 1 and by 2009 c 565 § 54, each without reference to the other. Both amendments are incorporated in the publication of this section under RCW 1.12.025(2). For rule of construction, see RCW 1.12.025(1).

Washington Forms by Issue

Washington Court Forms
> Probate
Washington Tax Forms

Washington Law

Washington State Laws
    > Washington Child Support
    > Washington Gun Laws
    > Washington Statute
Washington Court
    > Washington Courts
    > Washington State Court Records
    > Washington State Courts
Washington Labor Laws
    > Washington State Jobs
    > Washington State Unemployment
Washington State
    > Washington County Jail
    > Washington State Parks
Washington Tax
    > Washington State Tax
Washington Agencies
    > Washington DMV
    > Washington Secretary of State
    > Washington State Department of Health
    > Washington State Department of Licensing
    > Washington State Department of Revenue
    > Washington State Department of Transportation
    > Washington State Patrol

Washington Court Map

Tips